Back to previous page Ash Storage Facility, Aberthaw Power Station

Work TypeCivil Engineering
SectorWaste
StatusCompleted
LocationAberthaw, South Wales
ClientLaFarge Cement
Contract Period33 weeks


Building and civil engineering works for a five storey steel framed ash processing facility, which produces pulverised fuel ash (PFA) for use in concrete production.

 
Works included 11,000m3 earthworks and 320 driven piles

It includes a carbon return system that sends approximately 60,000 tonnes of unburnt fuel back to the power station for re-use.

Works involved;

  • 11,000m3 earthworks
  • 320 driven piles
  • Approximately 300 linear meters of slip-formed concrete drainage channel
  • Approximately 350 linear meters of reinforced ground beams


Website Design by Clickfire